MOVING ON

Lots of junk has been cleared out, and the plans for the counter and cafe service area have been finalised. The structural engineer will be visiting tomorrow, and then we will submit our application for planning permission for phase I.

GUTTED

Bob the electrician came on Sunday 24 January to make sense of, label, disconnect and generally make safe the unbelievable jungle of wiring in the shop. Then we bashed out the horrible chipboard counter, and underneath it our Treasurer found treasure indeed: £10.16 in grubby pence, some sweeties, and this little person.  

GOING GOING

On Thursday 7 January the first wave of volunteers swept in and cleared away the fixtures and fittings in the area of Phase 1. Only the shop counter was left in position until the electrician could disconnect the forest of wires. Many thanks to Sue, Edna, Alan, Jacqueline and Kathy for doing this dirty work.

IT’S OURS !!

As of today, we own the shop.  Eleven months on since that first public meeting in the Lacy Thompson hall, we have achieved the first goal: to have premises in which we can develop the vision of “more than just a shop”.  

A GIANT STEP

Today at noon we signed the contract for the purchase of the shop premises. As soon as we have arranged insurance cover, within a day or two, we can exchange contracts and complete the purchase.